2009 cold recycling on California highways - the pilot project process works.
by Donald Matthews, Pavement Recycling; Chuck Valentine, Valentine
Surfacing Co.
Darren Coughlin, Coughlin Construction
Often a new roadway construction technology is not readily accepted by a contacting
agency due a perceived failures with the first few projects constructed. These "failures"
are often a result of the agency's lack of experience and poorly defined expectations
among the parties involved as opposed to problems with the technology itself. In
an attempt to successfully implement new pavement strategies and develop consistent
expectations, Caltrans developed a pilot project process through the Pavement Preservation
Task Group (PPTG). This pilot project process is intended to prevent hasty conclusions
and provide all "new" technologies an opportunity to succeed.
Nothing illustrates the success of the process better than the five CIR contracts
that were constructed by the State in 2009 (Table 1). Four different general contractors
utilizing three different recycling subcontractors constructed these five CIR projects
in three different districts. All five CIR projects were ultimately deemed a success,
however one of them experienced significant problems. In addition, valuable lessons
resulting in the continuing improvments of the CIR specification was the result
of all of them. The most significant one is the Caltrans pilot project process calling
for Just in Time Training (JITT) and post-construction reviews by the appropriate
PPTG Subtask group is a significant means for ensuring ultimate success of a technology.
Caltrans CIR contracts FY 09/10
|
Contract
|
Location
|
Prime contractor
|
Recycling contractor
|
CIR depth
|
Square yards
|
|
06-0K6904
|
Kern SR 33
MP 40.3/45.5
|
Granite Construction Co.
|
Pavement Recycling Systems, Inc.
|
4-inches
|
79,000
|
|
06-0J4404
|
Kern SR-33
MP 45.5/54.8
|
W. Jaxon Baker, Inc
|
Valentine Surfacing Co.
|
4-inches
|
136,056
|
|
06-0F7404
|
Kern SR 33
MP 54.8/59.0
|
Granite Construction Co.
|
Pavement Recycling Systems, Inc
|
4-inches
|
63,702
|
|
09-336604
|
Mono SR 108
MP 9.8/15.1
|
Sierra Nevada Construction
|
Coughlin Company, Inc
|
4-inches
|
83,200
|
|
02-1E9804
|
Plumas SR 36
SR 12.3/14.0
|
Knife River Construction
|
Pavement Recycling Systems, Inc
|
4-inches
|
42,342
|
The importance of good communication and good JITT is clearly illustrated in the
three District 6 recycling contracts. The three contracts for District 6 were all
on State Route 33 in Kern County. The three seperate contracts ran in series, immediately
adjacent to each other. The first CIR contract let, 06-0J4404, was also District
6's first attempt at cold recycling. This was the middle segment of the three projects
on SR 33. The project called for four inches of CIR followed by a HMA overlay in
some areas and a chip seal in other areas. As part of the mix design process, core
samples were gathered by W. Jaxon Baker, the prime contractor, and sent to Asphalt
Pavement and Recycling Technology (APART) to conduct the mix design in accordance
with project specifications. The mix design called for 3.5% Pass R emulsified recycling
agent from Western Emulsions, Inc. as the starting emulsion rate. As it turned out,
due to the logistics of the project, this project was the only one of the five CIR
projects in the State not to conduct JITT. This also turned out to be the CIR project
that experienced the most problems.
Early on in the recycle operation on SR 33, the reycling subcontractor, Valentine
Surfacing, recommended a reduction in the amount of emulsified recycling agent based
upon the initial laydown performance and appearnce. This reduction was discussed
among the prime contractor and Caltrans and it was agreed to reduce the emulsion
content to 3% to remain withinthe +/- 0.5% recommendation of the mix design. However,
after reducing the emulsion content to 3.0% the recycled material continued to appear
to Valentine to be on the rich side and concerns were voiced about the stability
of the mix when the weather in that area increased.
The daytime temperatures at the time of the recycling were mostly in the 70°
and 80° F range with a few days reaching the 90° F level. Further discussions
were held but it was decided to remain at the 3.0% emulsion rate with a concern
about veering too far from the mix design recommendaton.
After the roadway was recycled, it was allowed to cure and was released to temporary
traffic. During the curing period, temperatures in the area continued to climb into
the high 90° F range. At intersections on the project, heavy truck traffic turning
loads on to and off of the recycled pavement resulted in rutting and shoving of
the cold recycled material. Isolated repairs had to be made to those areas and the
project was eventually overlaid and chip sealed.
Granite Construction with Pavement Recycling Systems, Inc. as the subcontractor
constructed the other two CIR projects on SR 33. In these two sections of roadway,
JITT was conducted with all the parties beginning the project with a good undestanding
of the expectations. These two projects utilized the same emulsified recycling agent
and the same laboratory completed the mix designs. However, for these projects,
the design emulsion content was reduced to 2.5% with one of the projects necessitating
the emulsion to be reduced to 2.3% in some areas. These two projects were completed
at both ends of the recycled section of SR 33 without experiencing any shoving at
the intersections and truck access points.
District 2's CIR project on SR 36 in Plumas County, 02-1E9804, proved challenging
in a different way with respect to the distress of the existing pavement and the
esisting grades at intersections. However, good JITT provided all parties the clear
understanding and the means and measures to handle the project challenges, especially
at the difficult turnouts and abrupt stopping grades, General contractor, Knife
River Construction and its subcontractor, Pavement Recycling Systems, Inc., made
quick work in cold in-place recycling the approximate 42,000-sy project at four
inches deep and constructing the 0.15-feet HMA overlay.
Finally, the District 9 SR108 Sonora Junction CIR project, 09-336604, built by Sierra
Nevada Construction as the general and COughlin Construction Company as the recycling
contractor proved again the value of good communication and defined expectations.
This 7,000 feet evaluation Mono County project consisted of 5.5 miles of four-inch
CIR with the roadway expanded from 24-feet to 26-feet during the recycling process.
A final two-inch HMA overlay was used as the surface seal. The experiences gained
by District 9 as relayed during the post-construction review with the PPTG Recycling
Subtask Group, resulted in some significant refinements to the CIR specification,
By fully implementing the pilot project process, the CIR pilot projects completed
in 2009, and the resulting experiences gained by Caltrans provide the State with
confidence and it prepares to embark on an aggressive recycling initiave to make
the CIR strategy commonplace Statewide.
« Back to News